We have assembled an expert project team that will be delivering Phase 1 of the restoration of Oldway Mansion in Paignton.
Before any physical work starts, an expert team has been working behind the scenes to gather as much information as possible on the building.
Phase 1 of the Oldway Mansion restoration project is being funded by £1million committed by us, and £8million of government funding.
Work that has been carried out so far includes specialist survey and risk assessment work, including the completion of a dry rot survey, appointing a Conservation Architect who is preparing a listed building application, building up a programme of urgent repair work, carrying out emergency roof repairs and undertaking 3D survey work.
The 3D survey work is an important part of the project, as the information gathered will build a 3D model of the building, giving us a permanent record of the building as it stands today. The 3D model will serve as a crucial tool in the restoration process, providing detailed information that allows the design team, to provide the necessary specifications and drawn information, to allow the relevant applications to be made, and the physical works to follow on. It will also enable architects to visualise and respond to the buildings needs more accurately.
A safe expert was also bought in to ‘crack open a safe’ which had no means of being opened. The safe unfortunately did not contain the crown jewels to be able to fund the entire restoration project, but an interesting and unexpected element of the restoration project, nonetheless.
Between September and the end of the year, further preparation work is planned, with scaffolding being set outside the ball room to enable a roof repair and around the West Tower of the Banqueting Hall so detailed investigation works can take place, to fully assess the building.
Regular visitors to the grounds may also notice an Ecologist undertaking an ecology survey. Work started this week, with a further visit planned for next month.
It is anticipated that in early 2025, scaffolding will start to be erected to areas of the main Mansion in preparation for roof repair work to begin. Scaffolding will be in place, to the external walls of the building, and will be put in place over a few months. There are approximately 13 different types of roofs to the main Mansion, meaning that one section at a time will be carefully repaired. Roof repair work is expected to be completed by the end of 2027.
Cllr Chris Lewis, Deputy Leader and Cabinet Member for Place Development and Economic Growth, said; “This work is a major first step in restoring Oldway Mansion. Fully understanding and stabilising the building is necessary to prevent any further deterioration. This work will allow the project team to ensure that our restoration efforts are both effective and respectful of Oldway’s heritage.
“There is still a long way to go before the public will once again be able to fully enjoy the building, but we hope this milestone gives confidence to the community that the restoration project is moving forward.”
The grounds of Oldway remain open for visitors.
Watch
News archive
- November 2024 (27)
- October 2024 (21)
- September 2024 (17)
- August 2024 (7)
- July 2024 (24)
- June 2024 (8)
- May 2024 (25)
- April 2024 (19)
- March 2024 (17)
- February 2024 (16)
- January 2024 (14)
- December 2023 (14)
- November 2023 (30)
- October 2023 (21)
- September 2023 (22)
- August 2023 (18)
- July 2023 (17)
- June 2023 (14)
- May 2023 (11)
- April 2023 (9)
- March 2023 (36)
- February 2023 (22)
- January 2023 (26)
- December 2022 (18)
- November 2022 (24)
- October 2022 (18)
- September 2022 (13)
- August 2022 (15)
- July 2022 (22)
- June 2022 (14)
- May 2022 (35)
- April 2022 (23)
- March 2022 (32)
- February 2022 (18)
- January 2022 (14)
- December 2021 (22)
- November 2021 (22)
- October 2021 (25)
- September 2021 (23)
- August 2021 (18)
- July 2021 (26)
- June 2021 (24)
- May 2021 (21)
- April 2021 (21)
- March 2021 (33)
- February 2021 (30)
- January 2021 (27)
- December 2020 (24)
- November 2020 (37)
- October 2020 (29)
- September 2020 (27)
- August 2020 (22)
- July 2020 (37)
- June 2020 (38)
- May 2020 (39)
- April 2020 (36)
- March 2020 (22)
- February 2020 (10)
- January 2020 (18)
- December 2019 (7)
- November 2019 (11)
- October 2019 (15)
- September 2019 (16)
- August 2019 (8)
- July 2019 (9)
- June 2019 (7)
- May 2019 (16)
- April 2019 (11)
- March 2019 (11)
- February 2019 (7)
- January 2019 (11)
- December 2018 (11)
- November 2018 (14)
- October 2018 (14)
- September 2018 (9)
- August 2018 (7)
- July 2018 (19)
- June 2018 (21)
- May 2018 (7)
- April 2018 (10)
- March 2018 (35)
- February 2018 (9)
- January 2018 (15)
- December 2017 (9)
- November 2017 (17)
- October 2017 (11)
- September 2017 (6)
- August 2017 (7)
- July 2017 (13)
- June 2017 (22)
- May 2017 (16)
- April 2017 (8)
- March 2017 (9)
- February 2017 (9)
- January 2017 (4)
- December 2016 (10)
- November 2016 (11)
- October 2016 (14)
- September 2016 (9)
- August 2016 (10)
- July 2016 (11)
- June 2016 (4)
- May 2016 (20)
- April 2016 (14)
- March 2016 (18)
- February 2016 (8)
- January 2016 (15)
- December 2015 (13)
- November 2015 (19)
- October 2015 (17)
- September 2015 (8)
- August 2015 (6)
- July 2015 (19)
- June 2015 (11)
- May 2015 (20)
- April 2015 (14)
- March 2015 (15)
- February 2015 (13)
- January 2015 (17)
- December 2014 (17)
- November 2014 (18)
- October 2014 (14)
- September 2014 (17)
- August 2014 (16)
- July 2014 (10)
- June 2014 (8)
- May 2014 (1)
- February 2014 (1)
- January 0001 (1)