Western Corridor Improvements - Compulsory Purchase Order

10/02/2015 - Western Corridor Improvement, Paignton - Spruce Way to Churscombe Cross - Acquisition of Land - Compulsory Purchase Order (Mayoral Decision)

(i)         that that Head of Estates use his delegated authority to continue negotiations with the landowners for acquisition of the land required for the Western Corridor scheme to completion and to acquisition by agreement when possible;

 

(ii)        that authority be delegated to the Executive Head of Commercial Services to make a Compulsory Purchase Order for the land required for the Western Corridor Highway Improvement Scheme affecting land adjacent to the A380 Kings Ash Road in accordance with the following:-

 

That Torbay Council makes a Compulsory Purchase Order under sections 239, 240, 249, 250 and 260 of the Highways Act 1980 for the acquisition of all interests in the land (except those already owned by the Council) and new rights within areas shown (shaded pink for areas of land in respect of which all interests are to be acquired and shaded blue for the areas over which new rights are to be acquired) on plan number 8/9/14_06 attached as Appendix 1 for the purpose of highway improvement.

 

(iii)       that the Executive Head of Commercial Services be authorised to:-

 

(a)       take all necessary steps to secure the making, confirmation and implementation of the Compulsory Purchase Order including the publication and service of all notices and the presentation of the Council’s case at any Public Inquiry;

 

(b)       acquire interests in land and new rights within the Compulsory Purchase Order either by agreement or compulsorily; and

 

(c)        approve agreements with land owners setting out terms for the withdrawal of objections to the Order, including where appropriate seeking exclusion of land or new rights form the Order; and

 

(iv)       that detailed design and preparation of proposals continue for the highway improvement scheme in order that a scheme can be implemented following acquisition of all required sections of land.