South Devon Link Road - Use of Local Labour - Update
Meeting: 19/06/2013 - Overview and Scrutiny Board (Item 8)
8 South Devon Link Road - Use of Local Labour - Update PDF 168 KB
To consider the update report on the use of local labour in the construction of the South Devon Link Road.
Minutes:
Following its meeting in September 2012, the Board had requested an update on the use of local labour within the contract to construct the South Devon Link Road.
Whilst the contract did not include specific clauses that required the contractor to use a set percentage of local labour or sub-contractors, it was noted that 62% of the 37 full time staff on site were recruited locally (with it envisaged that, when the full team of 45 staff were in place, 54% would be recruited locally). In addition, 53% of the 30 sub-contractors were either based locally or had a local regional office.
During the course of the debate members highlighted the effective communications strategy being employed by Galliford Try (the contractor) and asked questions in relation to the archaeological implications of the construction of the road.
Resolved: (i) that the Board welcomes the encouraging progress being made in the construction of the South Devon Link Road and is pleased with the levels of local labour being utilised; and
(ii) that a full update on the progress of the construction of the road be received in six months time.
Contact Governance Support
- Email: governance.support@torbay.gov.uk
- Tel: 01803 207087
- Fax: 01803 207112
- Torbay Council
Town Hall
Castle Circus
Torquay
TQ1 3DR
- Brixham Town Council
- Budget digest
- Calendar
- Civic Mayor
- Committees
- Constitution
- Councillors' allowances
- Councillors' behaviour, interests and standards
- Decisions
- Decision lists
- Forward plans
- Get involved and have your say
- How the Council works
- Independent remuneration panel
- Meetings
- Outside bodies
- Overview & Scrutiny
- Search documents
- Subscribe to updates
- What's new
- Your Councillors
- Your MPs
- Become a Councillor