Decision details

Environmental Enforcement Pilot

Decision Maker: Elected Mayor

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

In July 2015, the Mayor made a decision to commence a 12 month environmental crime pilot project, following the outcome of a competitive tendering process.  The 12 month project is due to be completed in September 2016.

A decision is therefore required on the future of the environmental crime project and what functions should it perform to improve visibility, increase enforcement and re-educate the wider public of the negative impact of environmental crime on the community.

Decision:

That a 2 year extension be granted to the environmental crime enforcement scheme with the current provider.

Reasons for the decision:

To progress the current pilot which is due to end in September 2016.

Alternative options considered:

Alternative options explored are set out in the submitted report.

Implementation:

This decision will come into force and may be implemented on 20 April 2016 unless the call-in procedure is triggered (as set out in the Standing Orders in relation to Overview and Scrutiny).

Information:

In July 2015, the Council commenced a 12 month environmental crime pilot project with 3GS.  The project is due to be completed in September 2016.  The current scheme provides a mechanism to tackle environmental issues such as litter and dog fouling through the issuing of Fixed Penalty Notices (FPNs).  The intention of the programme is to encourage the public to become more compliant with fewer offences committed and any income generated used to offset costs associated with FPNs as well as increasing awareness and compliance.  The submitted report set out an evaluation of the trial and a proposal to continue with the scheme.

 

The Mayor considered the recommendations of the Council made on 7 April 2016 and his decision is set out above.

Interests and Nature of Interests Declared:

None

Publication date: 12/04/2016

Date of decision: 07/04/2016

Effective from: 20/04/2016