Decision details

Brixham Town Centre Car Park Redevelopment

Decision Maker: Elected Mayor

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

A decision from the Mayor is required to amend the contract in light of the decision by the Development Management Committee on 6 March 2013 and the planning obligations required as part of that decision. The amendment is to the purchase price payable by the developer pursuant to the contract to take into account the level of planning contribution payable.

Decision:

That the purchase price payable pursuant to the contract be reduced by the same amount as that to be paid directly by the developer to the Council in Section 106 contributions.

Reasons for the decision:

The development does not remain viable with the additional cost of the required Section 106 contributions due to the significant site contamination and flood alleviation works necessary.  The decision will result in the Section 106 monies being spent within Brixham and for its community rather than elsewhere in Torbay.

Alternative options considered:

None

Implementation:

This decision will come into force and may be implemented on Wednesday, 29 May 2013 unless the call-in procedure is triggered (as set out in the Standing Orders in relation to Overview and Scrutiny).

Information:

The contract entered into with Tesco Stores Ltd for the redevelopment of Brixham town centre car park included a term that the purchase price of £2,000,000 was calculated on the assumption that the developer would not be required to make any further payments to the Council acting in any other capacity or to third parties. 

 

The Development Management Committee granted planning permission on 6 March 2013 subject to a number of conditions which included the developer to enter in to a Section 106 agreement to pay a contribution of approximately £285,000.  It is considered that the additional sum required by the Section 106 agreement and the significant site contamination and flood alleviation works necessary would make the development unviable.

 

The Mayor supported the recommendations of the Council made on 15 May 2013, as set out in his decision above.

Interests and Nature of Interests Declared:

None

Publication date: 20/05/2013

Date of decision: 15/05/2013

Effective from: 29/05/2013