Governance and Commissioning Review of Local Authority Company - SWISCo
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decision:
1. That the Cabinet approves the adoption and implementation with immediate effect of the recommendations as set out in Appendix 1 of the Governance and Commissioning Review of SWISCo (Section 7, 1-12.);
2. That the Cabinet approves the extension of the commissioning of SWISCo, as a wholly owned company of the Council to carry out the works specified in SWISCo Commissioning Agreements for a further 5 year period between 1st April 2025 and 31st March 2030; and
3. That the Director of Pride in Place in consultation with the Director of Finance and Cabinet Member for Pride in Place, Culture & Events and Parking be delegated authority to approve any revisions to the Councils commissioning agreement with SWISCo to the 31st March 2030.
Reasons for the decision:
The commissioning agreement of SWISCo spanning the five-year period 2020 to 2025 sets out that both parties shall undertake a review at the end of years 2, 5 and 10 of this agreement to ensure that governance arrangements and commissioning processes were robust and effective and provide sufficient direction for the management of SWISCo.
Alternative options considered:
Appendix 1 to the submitted report sets out a range of findings and recommendations in relation to how the council governs and commissions SWISCo. The recommendations were based on best practise guidance and take into account consequences of not adopting these recommendations.
Implementation:
This decision will come into force and may be implemented on 8 May 2024 unless the call-in procedure is triggered (as set out in the Standing Orders in relation to Overview and Scrutiny).
Information:
Torbay Council established SWISCo in 2020 as a wholly owned company of Torbay Council. The commissioning agreement of SWISCo sets out that both parties shall undertake a review at the end of years 2, 5 and 10 to ensure that governance arrangements and commissioning processes were robust and effective and provide sufficient direction for the management of SWISCo.
The purpose of the review was to provide recommendations relating to the Governance and Commissioning of SWISCo as a wholly owned company of the Council and to make a recommendation on any extension to the commissioning agreement from 1st April 2025 for a further 5 years.
At the meeting Councillor Billings proposed and Councillor Bye seconded a motion that was agreed unanimously by the Cabinet, as set out above.
Interests and Nature of Interests Declared:
None.
Publication date: 29/04/2024
Date of decision: 25/04/2024
Effective from: 08/05/2024
Contact Governance Support
- Email: governance.support@torbay.gov.uk
- Tel: 01803 207087
- Fax: 01803 207112
- Torbay Council
Town Hall
Castle Circus
Torquay
TQ1 3DR
- Brixham Town Council
- Budget digest
- Calendar
- Civic Mayor
- Committees
- Constitution
- Councillors' allowances
- Councillors' behaviour, interests and standards
- Decisions
- Decision lists
- Forward plans
- Get involved and have your say
- How the Council works
- Independent remuneration panel
- Meetings
- Outside bodies
- Overview & Scrutiny
- Search documents
- Subscribe to updates
- What's new
- Your Councillors
- Your MPs
- Become a Councillor